Test: Transportation & Assignment Model - Mechanical Engineering MCQ

10 questions mcq test - test: transportation & assignment model, which of the following is needed to use the transportation model.

Capacity of the sources

Demand of the destinations

Unit shipping cost

All of these

Which method usually gives a very good solution to the assignment problem?

Northwest corner rule

Vogel's approximation method

MODI method

Stepping-stone method

1 Crore+ students have signed up on EduRev. Have you?

In applying Vogel’s approximation method to a profit maximation problem, row and column penalties are determined by

finding the largest unit cost in each row or column.

finding the sum of the unit costs in each row or column.

finding the difference between the two highest unit costs in each row and column.

finding the difference between the two lowest unit costs in each row and column.

The concept of Vogel’s Approximation Method can be well understood through an illustration given below :

 The difference between two least cost cells are calculated for each row and column, which can be seen in the iteration given for each row and column.

assignment model mcq

Which one of the following is riot the solution method of transportation method?

Hungarian method

North west corner method

Least cost method

Vogel’s approximate method

The matrix in assignment model is

square maxtrix

rectangular matrix

diagonal matrix

unit matrix

Assignment model can be solved by conventional linear programming approach or transportation model approach, it is square matrix, having equal number of rows and columns. The objective is to assign one item from row to one item from column so that total cost of assignement is minimum.

In order for a transportation matrix which has six rows and four columns not to degenerate, what is the number of occupied cells, in the matrix?

Number of cells for non-degenerate solution  = 6 + 4 - 1 = 9

Consider the following statements: 1. For the application of optimally test in case of transportation model, the number of allocations should be equal to (m + n) where m is the number of rows and n is the number of columns. 2. Transportation problem is a special case of a linear programming problem. 3. In case of assignment problem, the first step is to dummy row or a matrix by adding a dummy row or a dummy column.

Which of these statements is/are correct?

1 and 2 only

2 and 3 only

Consider the following statements on transportation problem: 1. In Vogel’s approximation method, priority allotment is made in the cell with the lowest cost. 2. The North-west corner method ensures faster optimal solution. 3. If the total demand is higher than the supply, transportation problem cannot be solved. 4. A feasible solution may not be an optimal solution.

Which of these statements are correct?

Penalty cost method is

North West corner method

Vogel’s approximation method

None of the above

One disadvantage of using North-West Corner Rule to find initial solution to the transportation problem is that

it is complicated to use

it does not ’take into account cost of transportation

it leads to a degenerate initial solution

all of the above

--> and get INR 200 additional OFF

Top Courses for Mechanical Engineering

assignment model mcq

Important Questions for Transportation & Assignment Model

Transportation & assignment model mcqs with answers, online tests for transportation & assignment model.

cation olution
Join the 10M+ students on EduRev

Welcome Back

Create your account for free.

assignment model mcq

Forgot Password

Mcqmate logo

270+ Operations Research Solved MCQs

1.
A. objective function
B. decision variable
C. constraints
D. opportunity cost
Answer» A. objective function
2.
A. infeasible region
B. unbounded region
C. infinite region
D. feasible region
Answer» D. feasible region
3.
A. outgoing row
B. key row
C. basic row
D. interchanging row
Answer» C. basic row
4.
A. dummy
B. epsilon
C. penalty
D. regret
Answer» B. epsilon
5.
A. ncwr
B. lcm
C. vam
D. hungarian
Answer» D. hungarian
6.
A. head path
B. sub path
C. critical path
D. sub critical path
Answer» C. critical path
7.
A. 7
B. 10
C. 18
D. 8
Answer» B. 10
8.
A. interfering float = total float – free float
B. total float =free float + independent float
C. total float ≄ free float ≄ independent float
D. free float = total float – head event slack
Answer» B. total float =free float + independent float
9.
A. expected
B. pessimitic
C. optimistic
D. most likely
Answer» C. optimistic
10.
A. processing order
B. idle time
C. processing time
D. elapsed time
Answer» D. elapsed time
11.
A. physical
B. symbolic
C. deterministic
D. probabilistic
Answer» C. deterministic
12.
A. physical
B. symbolic
C. deterministic
D. probabilistic
Answer» D. probabilistic
13.
A. cpm and pert
B. assignment & transportation
C. game theory
D. decision theory & inventory models
Answer» A. cpm and pert
14.
A. objective function
B. decision variables
C. constraints
D. opportunity cost
Answer» B. decision variables
15.
A. objective function
B. decision variables
C. constraints
D. opportunity cost
Answer» A. objective function
16.
A. objective function
B. variables
C. constraints
D. profit
Answer» C. constraints
17.
A. infeasible
B. unbounded
C. improper
D. unknown
Answer» A. infeasible
18.
A. less than or equal to
B. greater than or equal to
C. mixed
D. equal to
Answer» D. equal to
19.
A. infeasible
B. infinite
C. unique
D. degenerate
Answer» B. infinite
20.
A. key column
B. incoming column
C. important column
D. variable column
Answer» A. key column
21.
A. vital element
B. important element
C. basic element
D. key element
Answer» D. key element
22.
A. surplus
B. artificial
C. slack
D. additional
Answer» C. slack
23.
A. null resource
B. scarce resource
C. abundant resource
D. zero resource
Answer» B. scarce resource
24.
A. either zero or positive
B. either zero or negative
C. only positive
D. only negative
Answer» A. either zero or positive
25.
A. vogel’s approximat ion method
B. nwcr
C. lcm
D. modi
Answer» C. lcm
26.
A. infeasible solution
B. feasible solution
C. optimum solution
D. degenerate solution
Answer» B. feasible solution
27.
A. infeasible solution
B. feasible solution
C. non degenerate solution
D. degenerate solution
Answer» C. non degenerate solution
28.
A. vam
B. nwcr
C. modi
D. lcm
Answer» A. vam
29.
A. balanced
B. unbalanced
C. infeasible
D. unbounded
Answer» B. unbalanced
30.
A. vam
B. nwcr
C. modi
D. hungarian
Answer» D. hungarian
31.
A. cost
B. regret
C. profit
D. dummy
Answer» B. regret
32.
A. critical
B. sub-critical
C. best
D. worst
Answer» A. critical
33.
A. tentative
B. definite
C. latest
D. earliest
Answer» C. latest
34.
A. machines order
B. job order
C. processing order
D. working order
Answer» C. processing order
35.
A. processing
B. waiting
C. free
D. idle
Answer» D. idle
36.
A. objective function
B. decision variables
C. constraints
D. opportunity cost
Answer» C. constraints
37.
A. less than
B. greater than
C. not greater than
D. not less than
Answer» A. less than
38.
A. infeasible
B. infinite
C. unbounded
D. feasible
Answer» D. feasible
39.
A. multiple constraints
B. infinite constraints
C. infeasible constraints
D. mixed constraints
Answer» D. mixed constraints
40.
A. outgoing row
B. key row
C. interchanging row
D. basic row
Answer» B. key row
41.
A. null resource
B. scarce resource
C. abundant resource
D. zero resource
Answer» C. abundant resource
42.
A. unit price
B. extra price
C. retail price
D. shadow price
Answer» D. shadow price
43.
A. either zero or positive
B. either zero or negative
C. only positive
D. only negative
Answer» B. either zero or negative
44.
A. vogel’s approximat ion method
B. nwcr
C. lcm
D. modi
Answer» A. vogel’s approximat ion method
45.
A. dummy
B. penalty
C. regret
D. epsilon
Answer» D. epsilon
46.
A. there is no degeneracy
B. degeneracy exists
C. solution is optimum
D. problem is balanced
Answer» A. there is no degeneracy
47.
A. dummy
B. non-critical
C. important
D. critical
Answer» D. critical
48.
A. one
B. zero
C. highest
D. equal to duration
Answer» B. zero
49.
A. optimistic
B. pessimistic
C. expected
D. most likely
Answer» A. optimistic
50.
A. processing time
B. waiting time
C. elapsed time
D. idle time
Answer» C. elapsed time
51.
A. invitees
B. players
C. contestants
D. clients
Answer» B. players
52.
A. income
B. profit
C. payoff
D. gains
Answer» C. payoff
53.
A. choices
B. strategies
C. options
D. actions
Answer» B. strategies
54.
A. centre point
B. saddle point
C. main point
D. equal point
Answer» B. saddle point
55.
A. 2
B. 3
C. 1
D. 4
Answer» B. 3
56.
A. parallel to x axis
B. parallel to y axis
C. passes through the origin
D. intersects both the axis
Answer» A. parallel to x axis
57.
A. qualitative
B. quantitative
C. judgmental
D. subjective
Answer» B. quantitative
58.
A. exact
B. earliest
C. latest
D. approximate
Answer» B. earliest
59.
A. alternate
B. feasible solution
C. critical
D. sub-critical
Answer» D. sub-critical
60.
A. degenerate
B. prohibited
C. infeasible
D. unbalanced
Answer» B. prohibited
61.
A. Research
B. Decision – Making
C. Operations
D. None of the above
Answer» B. Decision – Making
62.
A. J.F. McCloskey
B. F.N. Trefethen
C. P.F. Adams
D. Both A and B
Answer» D. Both A and B
63.
A. 1950
B. 1940
C. 1978
D. 1960
Answer» B. 1940
64.
A. Civil War
B. World War I
C. World War II
D. Industrial Revolution
Answer» C. World War II
65.
A. Battle field
B. Fighting
C. War
D. Both A and B
Answer» D. Both A and B
66.
A. Morse and Kimball (1946)
B. P.M.S. Blackett (1948)
C. E.L. Arnoff and M.J. Netzorg
D. None of the above
Answer» A. Morse and Kimball (1946)
67.
A. E.L. Arnoff
B. P.M.S. Blackett
C. H.M. Wagner
D. None of the above
Answer» C. H.M. Wagner
68.
A. C. Kitte
B. H.M. Wagner
C. E.L. Arnoff
D. None of the above
Answer» A. C. Kitte
69.
A. Scientists
B. Mathematicians
C. Academics
D. All of the above
Answer» A. Scientists
70.
A. Economists
B. Administrators
C. Statisticians and Technicians
D. All of the above
Answer» D. All of the above
71.
A. System Orientation
B. System Approach
C. Interdisciplinary Team Approach
D. none
Answer» D. none
72.
A. Answers
B. Solutions
C. Both A and B
D. Decisions
Answer» C. Both A and B
73.
A. Quality
B. Clarity
C. Look
D. None of the above
Answer» A. Quality
74.
A. Scientific
B. Systematic
C. Both A and B
D. Statistical
Answer» C. Both A and B
75.
A. Two or more
B. One or more
C. Three or more
D. Only One
Answer» B. One or more
76.
A. Conducting experiments on it
B. Mathematical analysis
C. Both A and B
D. Diversified Techniques
Answer» C. Both A and B
77.
A. Policies
B. Actions
C. Both A and B
D. None of the above
Answer» C. Both A and B
78.
A. Science
B. Art
C. Mathematics
D. Both A and B
Answer» D. Both A and B
79.
A. Scientific Models
B. Algorithms
C. Mathematical Models
D. None of the above
Answer» C. Mathematical Models
80.
A. Quailing Theory
B. Waiting Line
C. Both A and B
D. Linear Programming
Answer» D. Linear Programming
81.
A. Inventory Control
B. Inventory Capacity
C. Inventory Planning
D. None of the above
Answer» C. Inventory Planning
82.
A. Inventory Control
B. Inventory
C. Inventory Planning
D. None of the above
Answer» B. Inventory
83.
A. Game Theory
B. Network Analysis
C. Decision Theory
D. None of the above
Answer» C. Decision Theory
84.
A. Game Theory
B. Network Analysis
C. Decision Theory
D. None of the above
Answer» B. Network Analysis
85.
A. Simulation
B. Integrated Production Models
C. Inventory Control
D. Game Theory
Answer» A. Simulation
86.
A. Search Theory
B. Theory of replacement
C. Probabilistic Programming
D. None of the above
Answer» B. Theory of replacement
87.
A. Probabilistic Programming
B. Stochastic Programming
C. Both A and B
D. Linear Programming
Answer» C. Both A and B
88.
A. Programme Evaluation
B. Review Technique (PERT)
C. Both A and B
D. Deployment of resources
Answer» C. Both A and B
89.
A. Schedule
B. Product Mix
C. Both A and B
D. Servicing Cost
Answer» C. Both A and B
90.
A. Men and Machine
B. Money
C. Material and Time
D. All of the above
Answer» D. All of the above
91.
A. Three
B. Four
C. Five
D. Two
Answer» A. Three
92.
A. Sequencing
B. Allocation Models
C. Queuing Theory
D. Decision Theory
Answer» B. Allocation Models
93.
A. Linear Programming Technique
B. Non – Linear Programming Technique
C. Both A and B
D. None of the above
Answer» C. Both A and B
94.
A. Deterministic Models
B. Probabilistic Models
C. Both A and B
D. None of the above
Answer» A. Deterministic Models
95.
A. Deterministic Models
B. Probabilistic Models
C. Both A and B
D. None of the above
Answer» B. Probabilistic Models
96.
A. Iconic Models
B. Analogue Models
C. Symbolic Models
D. None of the above
Answer» A. Iconic Models
97.
A. Optimum
B. Perfect
C. Degenerate
D. None of the above
Answer» A. Optimum
98.
A. Research
B. Operation
C. Both A and B
D. None of the above
Answer» B. Operation
99.
A. Decision Theory
B. Simulation
C. Game Theory
D. None of the above
Answer» B. Simulation
100.
A. Queuing Theory
B. Decision Theory
C. Both A and B
D. None of the above
Answer» A. Queuing Theory

Done Reading?

  • Question and answers in Operations Research,
  • Operations Research multiple choice questions and answers,
  • Operations Research Important MCQs,
  • Solved MCQs for Operations Research,
  • Operations Research MCQs with answers PDF download

suLMS

  • Kopere Dashboard
  • Online Resources University Website AMS Students Module AMS Lectuter's Module (LAN ONLY) Attachment System Clearance System University Intranet (LAN ONLY) Safe Exam Browser (Windows) Safe Exam Browser (macOS) Password Reset (Staff) Password Reset (Students)
  • University Library Library Catalog Off-Campus Access SU Digital Repository ExamsBank (On-Campus) ExamsBank (Off-Campus) eBooks+ BigBlueButton
  • SBS eLearning
  • MAPE eLearning
  • Help Usage Tutorials FAQs+

Strathmore University eLearning System

Log in to Strathmore University eLearning System

Operations Research

101. All the basis for a transportation problem is ______________.

102. In the transportation table, empty cells will be called ______________.

103. ______________ is a completely degenerate form of a transportation problem

  • Transportation Problem
  • Assignment Problem
  • Travelling salesman problem
  • Replacement Problem

104. The linear function to be maximized or minimized is called ______________ function.

105. The coefficient of an artificial variable in the objective function of penalty method are always assumed to be ______________.

106. The process that performs the services to the customer is known as ______________.

  • service channel

107. A queuing system is said to be a ______________ when its operating characteristic are dependent upon time

  • pure birth model
  • pure death model
  • transient state
  • steady state

108. Slack is also known as ______________.

109. What type of distribution does a time follow in program evaluation review technique model?

  • Exponential

110. A activity in a network diagram is said to be ______________ if the delay in its start will further delay the project completion time.

  • critical path
  • non critical

Search MBA MCQ.com

Assignment Problem: Meaning, Methods and Variations | Operations Research

assignment model mcq

After reading this article you will learn about:- 1. Meaning of Assignment Problem 2. Definition of Assignment Problem 3. Mathematical Formulation 4. Hungarian Method 5. Variations.

Meaning of Assignment Problem:

An assignment problem is a particular case of transportation problem where the objective is to assign a number of resources to an equal number of activities so as to minimise total cost or maximize total profit of allocation.

The problem of assignment arises because available resources such as men, machines etc. have varying degrees of efficiency for performing different activities, therefore, cost, profit or loss of performing the different activities is different.

Thus, the problem is “How should the assignments be made so as to optimize the given objective”. Some of the problem where the assignment technique may be useful are assignment of workers to machines, salesman to different sales areas.

Definition of Assignment Problem:

ADVERTISEMENTS:

Suppose there are n jobs to be performed and n persons are available for doing these jobs. Assume that each person can do each job at a term, though with varying degree of efficiency, let c ij be the cost if the i-th person is assigned to the j-th job. The problem is to find an assignment (which job should be assigned to which person one on-one basis) So that the total cost of performing all jobs is minimum, problem of this kind are known as assignment problem.

The assignment problem can be stated in the form of n x n cost matrix C real members as given in the following table:

assignment model mcq

Hungarian Method for Solving Assignment Problem:

The Hungarian method of assignment provides us with an efficient method of finding the optimal solution without having to make a-direct comparison of every solution. It works on the principle of reducing the given cost matrix to a matrix of opportunity costs.

Opportunity cost show the relative penalties associated with assigning resources to an activity as opposed to making the best or least cost assignment. If we can reduce the cost matrix to the extent of having at least one zero in each row and column, it will be possible to make optimal assignment.

The Hungarian method can be summarized in the following steps:

Step 1: Develop the Cost Table from the given Problem:

If the no of rows are not equal to the no of columns and vice versa, a dummy row or dummy column must be added. The assignment cost for dummy cells are always zero.

Step 2:  Find the Opportunity Cost Table:

(a) Locate the smallest element in each row of the given cost table and then subtract that from each element of that row, and

(b) In the reduced matrix obtained from 2 (a) locate the smallest element in each column and then subtract that from each element. Each row and column now have at least one zero value.

Step 3: Make Assignment in the Opportunity Cost Matrix:

The procedure of making assignment is as follows:

(a) Examine rows successively until a row with exactly one unmarked zero is obtained. Make an assignment single zero by making a square around it.

(b) For each zero value that becomes assigned, eliminate (Strike off) all other zeros in the same row and/ or column

(c) Repeat step 3 (a) and 3 (b) for each column also with exactly single zero value all that has not been assigned.

(d) If a row and/or column has two or more unmarked zeros and one cannot be chosen by inspection, then choose the assigned zero cell arbitrarily.

(e) Continue this process until all zeros in row column are either enclosed (Assigned) or struck off (x)

Step 4: Optimality Criterion:

If the member of assigned cells is equal to the numbers of rows column then it is optimal solution. The total cost associated with this solution is obtained by adding original cost figures in the occupied cells.

If a zero cell was chosen arbitrarily in step (3), there exists an alternative optimal solution. But if no optimal solution is found, then go to step (5).

Step 5: Revise the Opportunity Cost Table:

Draw a set of horizontal and vertical lines to cover all the zeros in the revised cost table obtained from step (3), by using the following procedure:

(a) For each row in which no assignment was made, mark a tick (√)

(b) Examine the marked rows. If any zero occurs in those columns, tick the respective rows that contain those assigned zeros.

(c) Repeat this process until no more rows or columns can be marked.

(d) Draw a straight line through each marked column and each unmarked row.

If a no of lines drawn is equal to the no of (or columns) the current solution is the optimal solution, otherwise go to step 6.

Step 6: Develop the New Revised Opportunity Cost Table:

(a) From among the cells not covered by any line, choose the smallest element, call this value K

(b) Subtract K from every element in the cell not covered by line.

(c) Add K to very element in the cell covered by the two lines, i.e., intersection of two lines.

(d) Elements in cells covered by one line remain unchanged.

Step 7:  Repeat Step 3 to 6 Unlit an Optimal Solution is Obtained:

The flow chart of steps in the Hungarian method for solving an assignment problem is shown in following figures:

assignment model mcq

ADVERTISEMENTS:

Assignment problem is a special type of linear programming problem which deals with the allocation of the various resources to the various activities on one to one basis. It does it in such a way that the cost or time involved in the process is minimum and profit or sale is maximum. Though there problems can be solved by simplex method or by transportation method but assignment model gives a simpler approach for these problems.

In a factory, a supervisor may have six workers available and six jobs to fire. He will have to take decision regarding which job should be given to which worker. Problem forms one to one basis. This is an assignment problem.

1. Assignment Model :

Suppose there are n facilitates and n jobs it is clear that in this case, there will be n assignments. Each facility or say worker can perform each job, one at a time. But there should be certain procedure by which assignment should be made so that the profit is maximized or the cost or time is minimized.

job of Work

In the table, Co ij is defined as the cost when j th job is assigned to i th worker. It maybe noted here that this is a special case of transportation problem when the number of rows is equal to number of columns.

Mathematical Formulation:

Any basic feasible solution of an Assignment problem consists (2n – 1) variables of which the (n – 1) variables are zero, n is number of jobs or number of facilities. Due to this high degeneracy, if we solve the problem by usual transportation method, it will be a complex and time consuming work. Thus a separate technique is derived for it. Before going to the absolute method it is very important to formulate the problem.

Suppose x jj is a variable which is defined as

1 if the i th job is assigned to j th machine or facility

0 if the i th job is not assigned to j th machine or facility.

Now as the problem forms one to one basis or one job is to be assigned to one facility or machine.

Assignment Model

The total assignment cost will be given by

clip_image005

The above definition can be developed into mathematical model as follows:

Determine x ij > 0 (i, j = 1,2, 3…n) in order to

Assignment Model

Subjected to constraints

Assignment Model

and x ij is either zero or one.

Method to solve Problem (Hungarian Technique):

Consider the objective function of minimization type. Following steps are involved in solving this Assignment problem,

1. Locate the smallest cost element in each row of the given cost table starting with the first row. Now, this smallest element is subtracted form each element of that row. So, we will be getting at least one zero in each row of this new table.

2. Having constructed the table (as by step-1) take the columns of the table. Starting from first column locate the smallest cost element in each column. Now subtract this smallest element from each element of that column. Having performed the step 1 and step 2, we will be getting at least one zero in each column in the reduced cost table.

3. Now, the assignments are made for the reduced table in following manner.

(i) Rows are examined successively, until the row with exactly single (one) zero is found. Assignment is made to this single zero by putting square □ around it and in the corresponding column, all other zeros are crossed out (x) because these will not be used to make any other assignment in this column. Step is conducted for each row.

(ii) Step 3 (i) in now performed on the columns as follow:- columns are examined successively till a column with exactly one zero is found. Now , assignment is made to this single zero by putting the square around it and at the same time, all other zeros in the corresponding rows are crossed out (x) step is conducted for each column.

(iii) Step 3, (i) and 3 (ii) are repeated till all the zeros are either marked or crossed out. Now, if the number of marked zeros or the assignments made are equal to number of rows or columns, optimum solution has been achieved. There will be exactly single assignment in each or columns without any assignment. In this case, we will go to step 4.

4. At this stage, draw the minimum number of lines (horizontal and vertical) necessary to cover all zeros in the matrix obtained in step 3, Following procedure is adopted:

(iii) Now tick mark all the rows that are not already marked and that have assignment in the marked columns.

(iv) All the steps i.e. (4(i), 4(ii), 4(iii) are repeated until no more rows or columns can be marked.

(v) Now draw straight lines which pass through all the un marked rows and marked columns. It can also be noticed that in an n x n matrix, always less than ‘n’ lines will cover all the zeros if there is no solution among them.

5. In step 4, if the number of lines drawn are equal to n or the number of rows, then it is the optimum solution if not, then go to step 6.

6. Select the smallest element among all the uncovered elements. Now, this element is subtracted from all the uncovered elements and added to the element which lies at the intersection of two lines. This is the matrix for fresh assignments.

7. Repeat the procedure from step (3) until the number of assignments becomes equal to the number of rows or number of columns.

Related Articles:

  • Two Phase Methods of Problem Solving in Linear Programming: First and Second Phase
  • Linear Programming: Applications, Definitions and Problems

No comments yet.

Leave a reply click here to cancel reply..

You must be logged in to post a comment.

web statistics

Transportation Models And Network Models MCQs

Photo of author

By By Team EasyExamNotes

1. Which transportation model is used to determine the most efficient allocation of resources between multiple origins and destinations? a) Traveling Salesman Problem b) Shortest Route Problem c) Transportation Assignment Model d) Minimal Spanning Tree Answer: c) Transportation Assignment Model Explanation: The Transportation Assignment Model is specifically designed to optimize the allocation of resources (such as goods or services) from multiple origins to multiple destinations, taking into account various constraints like costs and capacities.

2. What does the Traveling Salesman Problem seek to minimize? a) Time taken to travel between cities b) Cost of traveling between cities c) Number of cities visited d) Distance traveled between cities Answer: d) Distance traveled between cities Explanation: The Traveling Salesman Problem aims to find the shortest possible route that visits each city exactly once and returns to the original city.

3. Which network model is used to find the shortest path between two nodes in a network? a) Minimal Spanning Tree b) Maximum Flow Model c) Shortest Route Problem d) Critical Path Method Answer: c) Shortest Route Problem Explanation: The Shortest Route Problem deals with finding the most efficient path between two specific nodes in a network, minimizing distance, time, or other relevant metrics.

4. What is the primary objective of a Minimal Spanning Tree in network models? a) Maximizing the flow between nodes b) Minimizing the number of connections c) Minimizing the total cost of connections d) Maximizing the number of nodes Answer: c) Minimizing the total cost of connections Explanation: A Minimal Spanning Tree seeks to connect all the nodes in a network with the minimum possible total cost, ensuring that every node is reachable while minimizing the sum of edge weights.

5. In which type of network model is the concept of “flow” central to its optimization? a) Shortest Route Problem b) Maximum Flow Model c) Transportation Assignment Model d) Critical Path Method Answer: b) Maximum Flow Model Explanation: The Maximum Flow Model aims to determine the maximum amount of flow that can pass through a network from a source to a sink, subject to capacity constraints on edges and nodes.

6. Which network model is commonly used for project management to schedule and organize tasks? a) Shortest Route Problem b) Critical Path Method c) Minimal Spanning Tree d) Transportation Assignment Model Answer: b) Critical Path Method Explanation: The Critical Path Method (CPM) is a project management tool used to schedule and organize tasks in a project, identifying the critical path – the longest sequence of dependent tasks – and determining the project’s overall duration.

7. What does PERT stand for in the context of project management networks? a) Project Evaluation and Review Technique b) Project Efficiency and Resource Tracking c) Program Evaluation and Resource Timeframe d) Project Execution and Resource Tracking Answer: a) Project Evaluation and Review Technique Explanation: PERT (Project Evaluation and Review Technique) is a method used in project management to analyze and represent the tasks involved in completing a project, incorporating uncertainty into the project’s schedule.

8. Which sequencing model aims to optimize the order of tasks to minimize total completion time? a) Traveling Salesman Problem b) Critical Path Method c) Shortest Route Problem d) Sequencing Model Answer: d) Sequencing Model Explanation: Sequencing models focus on determining the optimal order or sequence of tasks or jobs to minimize total completion time, cost, or other specified criteria.

9. What does CPM identify in a project management network? a) Maximum flow path b) Critical path c) Minimal spanning tree d) Shortest route Answer: b) Critical path Explanation: In a project management network, the Critical Path Method (CPM) identifies the critical path, which is the longest sequence of dependent tasks and determines the project’s minimum duration.

10. Which transportation model is concerned with the allocation of resources to minimize the total transportation cost? a) Shortest Route Problem b) Transportation Assignment Model c) Maximum Flow Model d) Traveling Salesman Problem Answer: b) Transportation Assignment Model Explanation: The Transportation Assignment Model focuses on allocating resources (such as goods or services) from multiple origins to multiple destinations in a way that minimizes the total transportation cost.

Related posts:

  • Stones, Brick, Mortar and Concrete MCQs
  • Timber ,Glass , Steel and Aluminium MCQS
  • Flooring , Roofing ,Plumbing and Sanitary Material MCQS
  • Paints, Enamels and Varnishes MCQs
  • Miscellaneous ConstructionMaterials MCQs
  • Surveying &Levelling MCQS
  • Theodolite Traversing MCQs
  • Tacheometry MCQS
  • Curves MCQS
  • Hydrographic Survey MCQs
  • Drawing of Building Elements MCQS
  • Building Planning MCQS
  • Building Services MCQs
  • Architectural Principles MCQs
  • Town Planning & Perspective Drawing MCQs
  • Simple Stress and Strains MCQs
  • Bending and Shearing Stresses MCQs
  • Beam Deflection Methods MCQs
  • Columns and Struts MCQs
  • Torsion of Shafts MCQs
  • Review of Fluid Properties MCQs
  • Kinematics of Flow MCQs
  • Dynamics of Flow MCQs
  • Laminar Flow MCQs
  • Fluid Mechanics MCQs
  • Highway Engineering MCQs
  • Bituminous & Cement Concrete Payments MCQS
  • Transportation Engineering MCQs
  • Airport Planning and Geometrical Elements MCQs
  • Airport, Obstructions, Lightning & Traffic control MCQs
  • Preliminary and detailed investigation methods MCQs
  • Construction equipments MCQs
  • Contracts MCQs
  • Specifications & Public Works Accounts MCQs
  • Site Organization & Systems Approach to Planning MCQs
  • Construction Estimation MCQs
  • Rate Analysis MCQs
  • Detailed Estimates MCQs
  • Cost of Works MCQS
  • Valuation MCQS
  • Marine Construction MCQs
  • Harbour Planning MCQs
  • Natural Phenomena MCQS
  • Marine Structures MCQs
  • Docks and Locks MCQS
  • Urban Planning MCQs
  • Urban Planning MCQs: Sustainability, Finance, and Emerging Concepts
  • Traffic transportation systems MCQs
  • Development plans MCQS
  • Remote Sensing MCQs
  • Remote Sensing Platforms and Sensors MCQS
  • Geographic Information System MCQS
  • Data Models mCQs
  • Integrated Applications of Remote sensing and GIS MCQs
  • Renewable Energy MCQs
  • Renewable Energy Systems Overview MCQ
  • Alternative Energy Sources MCQs
  • Electric Energy Conservation MCQs
  • Entrepreneurship MCQs
  • Motivation MCQS
  • Small Business Setup MCQs
  • Finance and Accounting MCQs
  • Entrepreneurial Sickness and Small Business Growth MCQs
  • Design features and construction of Foundations MCQs
  • Formwork and Temporary structures MCQs
  • Masonry and walls MCQS
  • Floor and Roof Construction MCQs
  • Earthquake-Resistant Building MCQs
  • Virtual work and Energy Principles MCQS
  • Indeterminate Structures-I MCQS
  • Indeterminate Structures – II MCQs
  • V Arches and Suspension Cables MCQS
  • Rolling loads and Influence Lines MCQS
  • Railway Track Construction MCQs
  • Railway Track Design and Signaling MCQs
  • Bridge Construction Essentials MCQs
  • Bridge Construction MCQs
  • Tunnels MCQS
  • Geology Earth’s Processes and Phenomena MCQs
  • Mineralogy and crystallography MCQs
  • Petrology MCQs
  • Structural geology MCQs
  • Geology, Remote Sensing, and GIS MCQs
  • Waste water Treatment Operations MCQs
  • Biological Treatment of waste-water MCQS
  • Advanced Waste-water treatment MCQS
  • Introduction of Air pollution MCQS
  • Air pollution chemistry MCQs
  • Undamped Single Degree of Freedom System MCQS
  • Damped Single Degree of Freedom System MCQ
  • Response to harmonic and periodic vibrations MCQS
  • Response to Arbitrary, Step, and Pulse Excitation MCQS
  • Multi Degree of Freedom System MCQS
  • Structural Engineering MCQs
  • Lift & Escalator MCQS
  • Fire-Fighting MCQs
  • Acoustics and sound insulation and HVAC system MCQS
  • Miscellaneous Services MCQS
  • Basic Principles of Structural Design MCQs
  • Design of Beams MCQs
  • Design of Slabs MCQS
  • Columns & Footings MCQs
  • Staircases MCQs
  • Water Resources MCQs
  • Water Supply Systems MCQs
  • Water Treatment methods MCQs
  • Sewerage Systems MCQS
  • Wastewater Analysis & Disposal MCQs
  • Irrigation water requirement and Soil-Water-Crop relationship MCQS
  • Ground Water and Well irrigation MCQs
  • Hydrology MCQs
  • Canals and Structures MCQs
  • Floods MCQS
  • Prefabrication in Construction MCQs
  • Prefabricated Construction MCQs
  • Design Principles MCQs
  • Structural Joint MCQs
  • Design of abnormal load MCQS
  • Advance Pavement Design MCQs
  • Flexible Pavements MCQS
  • Rigid Pavements MCQS
  • Rigid pavement design MCQs
  • Evaluation and Strengthening of Existing Pavements MCQS
  • Cost Effective & ECO-Friendly Structures MCQs
  • Cost effective construction techniques and equipments MCQs
  • Cost effective sanitation MCQS
  • Low Cost Road Construction MCQs
  • Cost analysis and comparison MCQ
  • Turbulent flow MCQS
  • Uniform flow in open channels MCQs
  • Non uniform flow in open channels MCQs
  • Forces on immersed bodies MCQs
  • Fluid Machines MCQs
  • Intellectual Property Rights MCQs
  • Copyright MCQs
  • Patents MCQs
  • Trade Marks, Designs & GI MCQs
  • Contemporary Issues & Enforcement of IPR MCQs
  • Concept of EIA MCQs
  • Methods of Impact Identification MCQs
  • Impact analysis MCQs
  • Preparation of written documentation MCQs
  • Public Participation in Environmental Decision making MCQs
  • Linear Models MCQs
  • Inventory Models MCQs
  • Queueing Models MCQS
  • Decision Models MCQs
  • Basis of Structural Design and Connection Design MCQS
  • Design of Compression and Tension Members MCQs
  • Design of Flexural Members MCQs
  • Design of Columns and Column Bases MCQs
  • Design of Industrial Buildings MCQS
  • Hydrological Cycle mCQs
  • Hydrological Measurement MCQs
  • Groundwater and Well Dynamics MCQs
  • Selection of foundation and Sub-soil exploration/investigation MCQs
  • Shallow Foundation MCQs
  • Pile foundations MCqs
  • Foundations on problematic soil & Introduction to Geosynthetics MCQs
  • Retaining Walls and Earth Pressure MCQs
  • Types of Bridge Super Structures MCQs
  • Design of R.C. Bridge MCQs
  • Design of Steel Bridges MCQs
  • Pier, Abutment and Wing Walls MCQs
  • Foundations and Bearings MCQs
  • Engineering Seismology MCQS
  • Response Spectrum MCQs
  • Aseismic Structural Modelling MCQS
  • Design of structure for earthquake resistance MCQS
  • Seismic control of structures MCQs
  • Introduction to Artificial Intelligence MCQs
  • Various types of production systems and search techniques MCQs
  • Knowledge Representation and Probabilistic Reasoning MCQS
  • Game playing techniques MCQs
  • Introduction to learning ,ANN MCQs
  • Concrete Structure MCQs
  • Damage Assessment MCQs
  • Influence on Serviceability and Durability MCQs
  • Maintenance and Retrofitting Techniques MCQs
  • Materials for Repair and Retrofitting MCQs
  • Paradigm Shift in Water Management MCQS
  • Sustainable Water Resources Management MCQs
  • Integrated Water Resources Management (IWRM) Approach MCQs
  • Surface and Subsurface Water Systems MCQS
  • Conventional and Non-conventional Techniques for Water Security MCQs
  • Cloud Computing MCQs
  • Computer Organization and Architecture MCQs
  • Advanced Computer Architecture MCQ
  • Social Issues and the Environment MCQ
  • Introduction to Digital Communication MCQ
  • Transform Calculus MCQ
  • Software Design MCQ
  • Multiprocessors MCQ
  • Software architecture models MCQ

Leave a Comment

Wallstreet Logo

Trending Courses

Course Categories

Certification Programs

  • Free Courses

Capital Budgeting Resources

  • Free Practice Tests
  • On Demand Webinars

Assignment Method

Published on :

21 Aug, 2024

Blog Author :

Edited by :

Reviewed by :

Dheeraj Vaidya

What Is The Assignment Method?

The assignment method is a strategic approach to allocating organizational resources, including tasks and jobs to various departments like people, machines, or teams. It aims to minimize total costs or completion time and gain maximum efficiency, by assigning resources to corresponding units.

Assignment Method

The assignment procedure's importance stems from its capacity to optimize resource allocation procedures in a business. Organizations may guarantee that resources are used optimally, reducing waste and increasing productivity by implementing a systematic method. It facilitates the decision-making process for the efficient and economical use of resources by helping to make well-informed choices.

Table of contents

Assignment method explained, methodology, advantages & disadvantages, frequently asked questions (faqs), recommended articles.

  • The assignment method strategically allocates resources to tasks, jobs or teams to minimize costs or completion time. It optimizes resource utilization, reduces waste, and improves operational efficiency.
  • It involves using methods like complete enumeration, simplex, transportation, or the Hungarian method. It involves using the assignment method of linear programming .
  • The   Hungarian assignment method efficiently solves assignment problems by determining optimal assignments using a cost matrix.
  • Advantages include structured resource allocation, enhanced resource utilization, and improved operational effectiveness. Limitations include data accuracy requirements and limited flexibility for dynamic changes.

The assignment method in operation research is a strategy for allocating organizational resources to tasks to increase profit via efficiency gains, cost reductions , and improved handling of operations that might create bottlenecks . It is an operations management tool that, by allocating jobs to the appropriate individual, minimizes expenses , time, and effort.

The technique is an essential tool for project management and cost accounting . It assists in allocating indirect expenses , such as overhead, to objects or cost centers according to predetermined standards, such as direct labor hours or required machine hours. The method helps determine the overall cost of every good or service, which helps with pricing, output, and resource distribution decisions. It also guarantees effective work allocation, on-time project completion, and economical use of resources. In short, it solves assignment problems.

Assignment problems involve assigning workers to specific roles, such as office workers or trucks on delivery routes, or determining which machines or products should be used in a plant during a specific period. Transportation problems involve distributing empty freight cars or assigning orders to factories. Allocation problems also involve determining which machines or products should be used to produce a given product or set of products. Unit costs or returns can be independent or interdependent, and if allocations affect subsequent periods, the problem is dynamic, requiring consideration of time in its solution.

The assignment problem can be solved using four methods: The complete enumeration method, the simplex method, the transportation method, and the Hungarian method.

The complete enumeration approach generates a list of potential assignments between resources and activities, from which the best option is chosen based on factors like cost, distance, time, or optimum profit. If the minimum cost, time, or distance for two or more assignments is the same, then this approach offers numerous optimal solutions. However If there are a lot of assignments, it is no longer appropriate for manual calculations. Assignment method calculators, if reliable, can be used for the same.

The simplex method can be solved as a linear programming problem using the simplex algorithm. The transportation method is a special case of the assignment problem. The method is, however, computationally inefficient for solving the assignment problem due to the solution's degeneracy problem.

The Hungarian assignment method problem, developed by mathematician D. Konig, is a faster and more efficient approach to solving assignment problems. It involves determining the cost of making all possible assignments using a matrix. Each problem has a row representing the objects to be assigned and columns representing assigned tasks. The cost matrix is square, and the optimum solution is to have only one assignment in a row or column. This method is a variation of the transportation problem, with the cost matrix being square and the optimum solution being one assignment in a row or column of the cost matrix.

Let us look into a few examples to understand the concept better.

TechLogistics Solutions, an imaginary delivery company, employs the assignment method to optimize the distribution of its delivery trucks. They meticulously consider distance, traffic conditions, and delivery schedules. TechLogistics efficiently allocates trucks to routes through strategic assignments, effectively reducing fuel costs and ensuring punctual deliveries. This method significantly enhances the company's operational efficiency and optimizes the utilization of its delivery resources.

Suppose XYZ Inc., a manufacturing company, is challenged to efficiently assign tasks to its machines (A, B, and C). Using the assignment method, XYZ calculates the cost matrix, reflecting the cost associated with each task assigned to each machine. Leveraging advanced algorithms like the Hungarian method, the company identifies optimal task-machine assignments, minimizing overall costs. This approach enables XYZ to streamline its production processes and enhance cost-effectiveness in manufacturing operations .

Advantages of the assignment method include:

  • Resource allocation is carried out in a structured and organized manner.
  • Enhancement of resource utilization to achieve optimal outcomes.
  • Facilitation of efficient distribution of tasks.
  • Improvement in operational effectiveness and productivity.
  • Economical allocation of resources.
  • Reduction in project completion time.
  • Consideration of multiple factors and constraints for informed decision-making.

The disadvantages of the assignment method are as follows:

  • Dependence on accurate and up-to-date data for effective decision-making.
  • Complexity when dealing with resource allocation on a large scale.
  • Subjectivity is involved in assigning values to the resource-requirement matrix.
  • Limited flexibility in accommodating dynamic changes or unforeseen circumstances.
  • Applicable primarily to quantitative tasks, with limitations in addressing qualitative aspects.

Johnson's rule is an operations research method that aims to estimate the optimal sequence of jobs in two work centers to reduce makespan. It optimizes the overall efficiency of the process. In contrast, the assignment method is useful for resource allocation, matching resources to specific tasks or requirements to optimize efficiency.

The study assignment method refers to the process of allocating students to specific courses or study programs based on their preferences, skills etc. It involves matching students with appropriate courses or programs to ensure optimal utilization of educational resources and meet individual student needs.

The assignment method is frequently employed when there is a requirement to allocate restricted resources like personnel, equipment, or budget to particular tasks or projects. It aids in enhancing resource utilization operational efficiency, and enables informed decision-making regarding resource allocation considering various factors and constraints.

This article has been a guide to what is Assignment Method. Here, we explain its methodologies, examples, advantages, & disadvantages. You may also find some useful articles here -

  • Cost Allocation Methods
  • Propensity Score Matching
  • Regression Discontinuity Design

Youtube

IMAGES

  1. Assignment Model MCQ

    assignment model mcq

  2. How to submit an mcq or file assignment 2019

    assignment model mcq

  3. 5th Semester Model MCQ Caribbean Social Problems

    assignment model mcq

  4. Assignment 1

    assignment model mcq

  5. Model MCQ For Online Paper

    assignment model mcq

  6. 40th BCS Preliminary MCQ Model Test Five

    assignment model mcq

VIDEO

  1. Geography

  2. NECO FURTHER MATHEMATICS OPERARIONAL RESEARCH

  3. Motivational interview assignment model

  4. MCQ 12

  5. MCQ 13

  6. MCQ 26

COMMENTS

  1. Transportation and Assignment Model Free MCQ Practice Test with

    The Test: Transportation & Assignment Model questions and answers have been prepared according to the Mechanical Engineering exam syllabus.The Test: Transportation & Assignment Model MCQs are made for Mechanical Engineering 2024 Exam. Find important definitions, questions, notes, meanings, examples, exercises, MCQs and online tests for Test ...

  2. Assignment MCQ [Free PDF]

    Get Assignment Multiple Choice Questions (MCQ Quiz) with answers and detailed solutions. Download these Free Assignment MCQ Quiz Pdf and prepare for your upcoming exams Like Banking, SSC, Railway, UPSC, State PSC. ... Solving by assignment model for minimization, Initially developing opportunity cost matrix by subtracting the smallest element ...

  3. PDF 4 UNIT FOUR: Transportation and Assignment problems

    4.3.2 Mathematical model of a transportation problem Before we discuss the solution of transportation problems we will introduce the notation used to describe the transportation problem and show that it can be formulated as a linear programming problem. We use the following notation; x ij= the number of units to be distributed from

  4. Assignment Model MCQ

    Get all study material quiz, articles, videos đŸŽ„, notes 📝, problems and solutions at single click for Operations Research50 + Videos35 + Lessons40 + Solved...

  5. Assignment Model in Operation Research

    Assignment Model in Operation Research - Examples and types. Page 1. Fundamentals of assignment model. Example 1: Balanced. Example 2: Multiple iterations. Example of maximization objective. Example 4: Unbalanced. Restrictions on assignments. Multiple optimal solutions.

  6. [Solved] Transportation Model MCQ [Free PDF]

    Get Transportation Model Multiple Choice Questions (MCQ Quiz) with answers and detailed solutions. Download these Free Transportation Model MCQ Quiz Pdf and prepare for your upcoming exams Like Banking, SSC, Railway, UPSC, State PSC. ... The assignment problem is a special case of transportation problem when each origin is associated with one ...

  7. PDF Unit 4 Lecturer notes of Assignment Problem of OR by Dr. G.R

    Jobs with costs of M are disallowed assignments. The problem is to find the minimum cost matching of machines to jobs. Fig 1 Matrix model of the assignment problem. The network model is in shown in Fig.2. It is very similar to the transportatio external flows are all +1 or -1. The only relevant parameter for the assignment model is arc cost

  8. 270+ Operations Research solved MCQs with PDF download

    Solved MCQs for Operations Research, with PDF download and FREE Mock test ... When a particular assignment in the given problem is not possible or restricted as a condition, it is called a problem. ... uses models built by quantitative measurement of the variables c a given problem and also derives a solution from the model using ...

  9. PDF THE ASSIGNMENT MODELS

    THE ASSIGNMENT MODELS a special case of the transportation model is the assignment model. This model is appropriate in problems, which involve the assignment of resources to tasks (e.g assign n persons to n different tasks or jobs). Just as the special structure of the transportation model allows for solution

  10. Operations Research

    Practice for BBA or MBA exams using these MCQ. Page 11. ... Assignment Problem; Travelling salesman problem; Replacement Problem; View answer. Correct answer: (B) Assignment Problem. ... pure birth model; pure death model; transient state; steady state; View answer. Correct answer: (C) transient state. 108.

  11. Assignment Problem: Meaning, Methods and Variations

    After reading this article you will learn about:- 1. Meaning of Assignment Problem 2. Definition of Assignment Problem 3. Mathematical Formulation 4. Hungarian Method 5. Variations. Meaning of Assignment Problem: An assignment problem is a particular case of transportation problem where the objective is to assign a number of resources to an equal number of activities so as to minimise total ...

  12. Assignment Problem in Linear Programming : Introduction and Assignment

    In a factory, a supervisor may have six workers available and six jobs to fire. He will have to take decision regarding which job should be given to which worker. Problem forms one to one basis. This is an assignment problem. 1. Assignment Model: Suppose there are n facilitates and n jobs it is clear that in this case, there will be n assignments.

  13. Transportation and assignment MCQs

    Transportation problem is basically a ( a) Maximisation model ( b) Minimisation model ( c) Trans-shipment problem ( d) Iconic model. The column, which is introduced in the matrix to balance the rim requirements, is known as: ( a) Key column ( b) Idle column ( c) Slack column ( d) Dummy Column. The row, which is introduced in the matrix to balance the rim requirement, is known as: ( a) Key row ...

  14. Operations Research MCQ [Free PDF]

    Get Operations Research Multiple Choice Questions (MCQ Quiz) with answers and detailed solutions. Download these Free Operations Research MCQ Quiz Pdf and prepare for your upcoming exams Like Banking, SSC, Railway, UPSC, State PSC. ... allowing it to model different scenarios, such as activities with skewed distributions or durations ...

  15. Transportation Models And Network Models MCQs

    a) Shortest Route Problem. b) Maximum Flow Model. c) Transportation Assignment Model. d) Critical Path Method. Answer: b) Maximum Flow Model. Explanation: The Maximum Flow Model aims to determine the maximum amount of flow that can pass through a network from a source to a sink, subject to capacity constraints on edges and nodes. 6.

  16. PDF ASSIGNMENT PROBLEM

    MCQ QUESTIONS WITH ANSWER K.BHARATHI,SCSVMV. ASSIGNMENT PROBLEM 2 / 55. ... So as to minimize total cost or maximize total pro t of allocation. The problem of assignment arises because available resources such as men, machines etc. have varying degrees of e ciency for performing di erent activities, therefore, cost, pro t or loss of performing the

  17. PDF OPERATIONS RESEARCH Multiple Choice Questions

    a, b, and c are independent. a, b, and d are independent. d c. are independentb and d are i. dependent38. Consider the linear equation 2 x1 + 3 x2 - 4 x3 + 5 x4 = 10 How many basic and non. One variable is basic, three variables are non-basic. Two variables are basic, two variables are non-basic. e i.

  18. Assignment Method

    Assignment Method Explained. The assignment method in operation research is a strategy for allocating organizational resources to tasks to increase profit via efficiency gains, cost reductions, and improved handling of operations that might create bottlenecks.It is an operations management tool that, by allocating jobs to the appropriate individual, minimizes expenses, time, and effort.

  19. MCQ

    a. the model adequately represents the real-world system. b. the model is internally consistent and logical. c. the correct random numbers are used. d. enough trial runs are simulated. 5. The validation process involves making sure that a. the model adequately represents the real-world system. b. the model is internally consistent and logical.

  20. Ch 6.6 Flashcards

    Study with Quizlet and memorize flashcards containing terms like Model enrichment is:, True or false: People, vehicles, plants, or even time slots are considered as the assignees that can be assigned tasks under the consideration of an assignment problem., In an assignment problem, each task is assigned how many resources? and more.

  21. MCQ Assignment

    Chapter 1: Assignment Problem. Multiple Choice Questions (MCQ) The application of assignment problems is to obtain _____. a. only minimum cost. b. only maximum profit. c. minimum cost or maximum profit. d. assign the jobs. The assignment problem is said to be unbalanced if _____. a. number of rows is greater than number of columns. b.

  22. PRC 5 ITB Mcqs by Zahod Qavi

    prc 5 ITB mcqs by Zahod Qavi - Free download as PDF File (.pdf) or read online for free. PRC itb Mcqs by Zahid Qavi.